Auburndale's Next Wave of New Homes Is Waiting on a Sewer Pipe

At the Auburndale City Commission meeting on July 6, 2026, Vice Mayor Helms asked a question that rarely comes up in a guide to new homes. He said the commission kept having conversations where builders wanted to start building but couldn't connect, and he asked how many developments were stuck at that stage.

Community Development Director Julie Womble said the city has about 22 developer agreements overall. She estimated about 14 are tied to the Gapway Force Main project and about 10 or 11 are waiting only on the Southern Force Main.

If you're comparing Auburndale with other Polk County towns, keep that number in mind. Much of the city's approved housing growth is waiting on the city's own wastewater lines, so the timing of that growth will follow utility contracts.

A Building Permit Doesn't Mean the Home Can Hook Up to Sewer

This affects buyers through one specific clause. At the same July meeting, the commission amended its developer agreement with BSC Florida Investments Corp. Under the amendment, the developer can build, develop and get permits. The project still can't discharge into the city's collection system until Phases I and II of the Southern Force Main Reroute are both complete and operational, as determined by the city.

The July 6 commission minutes trace the requirement to a 2022 utility study by Chastain-Skillman. The study found that development on the site couldn't discharge into the city's wastewater system until the Southern Force Main reroute was completed, permitted and operational, and until planning and design for an expansion of the Regional Wastewater Treatment Plant were done.

Schaller Preserve got the same kind of amendment in March 2026. It lies in unincorporated Polk County but inside Auburndale's utility service area. The change allowed construction, including homes, and Polk County building permits to go ahead. It still withheld permission to discharge until both phases of the Southern line are running.

Auburndale has had this problem for a while. In September 2024, The Ledger reported that state law barred the city from issuing building permits without enough water and sewer capacity. At that time, large developments in the northern Lakes District near State Road 559 could do only "horizontal" work like roads and street lighting. The same report said the city had received about 30 developer requests, and it put the sewer upgrades at an estimated $20 million to $25 million.

In that report, the city expected at least one project to be finished by early 2025 and possibly all of them by December 2025. As of July 2026, city records still listed Phase I of the Southern Force Main as under construction. The amendments let builders go vertical before the pipe is finished. That moves the bottleneck from the permit to the sewer connection.

Who Is Waiting Behind Which Pipe

The developer agreements show which projects depend on which pipe. Here are the named projects in city records, with the sizes the city gave:

Project or developer Location Size in city records Wastewater dependency
DLD Development LLC Southeast corner of Lake Van Road and SR 559 About 325 homes on about 77 acres Southern Force Main reroute and Gapway Force Main Phase 2
Doherty Holdings Fortieth, LLC South of Old Dixie Highway, east of the Polk Parkway Multifamily on about 33 acres, unit count not stated Southern Force Main reroute, Regional WWTP planning and design
Gapway Grove Corporation Gapway Road 45 lots on about 68 acres Pace Road improvements, Southern and Gapway force mains, Regional WWTP planning and design
Lakeside Park Estates Phase II, by Citicommunities, LLC Lake Ariana Boulevard 41 single-family homes on about 12 acres Pace Road improvements, Southern and Gapway force mains, Regional WWTP planning and design
Schaller Preserve Community Unincorporated Polk, in the city's utility service area Not stated Both Southern Force Main phases
BSC Florida Investments Corp. 0 Bordeau Court, near Gaborone Boulevard, per The Ledger Not stated Both Southern Force Main phases

DLD Development is the largest project with a stated size, and it needs two separate lines. The November 17, 2025 minutes say development on that 77-acre site cannot go vertical or discharge until both the Southern Force Main reroute and Gapway Force Main Phase 2 are completed, permitted and operational. The same agreement says the city makes no representation or warranty about when that work will begin. Projects that depend on more than one pipe have to wait for the slowest one.

The Dates on Record

Phase I and Phase II of the Southern line have the firmest dates. The treatment plant has budget figures but no schedule yet. In order:

  1. August 18, 2025. The commission approved a $2,137,023.66 proposal from Killebrew, Inc. for Phase I. It runs from the Regional Wastewater Treatment Plant to the Tenoroc property.
  2. March 16, 2026. At a workshop, officials discussed Gapway Force Main phasing and easements. They described the plant expansion as raising capacity from 4 to 6 million gallons per day. They said design hadn't moved past preliminary investigation and feasibility work, and the delivery method was still undecided.
  3. June 1, 2026. The proposed budget set aside $3,325,000 for plant expansion design and engineering and $10,026,000 for construction in FY 2027. Another $16,501,000 for construction was proposed for FY 2028.
  4. October 5, 2026. Commissioners voted unanimously to approve Killebrew's $1,159,765.64 proposal for Phase II. The line runs from Tenoroc through an easement to the right-of-way west of the Polk Parkway, where it meets the existing force main. Public Utilities Director Bradford Thomas said this is the second of two phases and will complete the project.

The October 5 minutes also give the contract terms: 180 days to substantial completion and 210 days to final completion. One commissioner said he understood the work would start immediately. If it did, 180 days would fall in early April 2027. That's a contract term, not a promise of occupancy. The BSC and Schaller Preserve amendments also leave it to the city to decide when the Southern line counts as operational.

What the Countywide Numbers Don't Show

Countywide data won't show this waiting supply. In September 2026, the Lakeland–Winter Haven metro area, which is Polk County, recorded 905 single-family sales, down 8.8% from a year earlier, according to Florida Realtors. The median sale price was $325,000, down 1.5%.

The Lakeland REALTORS® August 2026 report shows its market tightening. Its MLS had 1,441 listings in inventory, down from 1,511 a year earlier, and months of inventory fell from 4.81 to 3.55. That association's area isn't limited to Auburndale or even to Polk County. About 78% of its listed sales were in Polk.

Builders are still filing countywide. Polk County recorded 510 new residential permits in August 2026, among the highest county totals in the Tampa region, according to a Florida Realtors report on permit data.

So the numbers buyers usually watch, like inventory, months of supply and permits, only count homes that exist or are being built. Auburndale's Southern and Gapway projects add another group that doesn't appear in those numbers yet. This is housing that has been approved and in some cases permitted, and it's waiting only on a sewer connection. When Phase II finishes, homes behind the Southern line could start reaching the market around the same time instead of one subdivision at a time. Projects that also need Gapway Phase 2 or treatment plant work will come later on their own schedule.

Where This Shows Up in a Purchase

New-build buyers face the most direct risk in Auburndale's growth area. A model home, a graded street and a permitted house don't show whether the community can connect to sewer. The developer agreement does. Before you sign, it's reasonable to ask the builder which force main the community depends on, whether the developer agreement has been amended to allow vertical construction ahead of tie-in, and how the closing date in your contract handles a delay in the city's operational date.

Resale buyers near SR 559, Lake Van Road and the Polk Parkway corridor have a different question. The empty or half-finished land near a home today may already be approved for hundreds of units. The table above shows several of those sites. City records name them and give their sizes, so you can look up a nearby parcel before you buy instead of guessing.

Sellers of established homes in the same area face a time limit on price comparisons. For now, they're mostly measured against other resale homes. Once the pipe is operational, they'll also be measured against new homes that are being built now and can't close yet.

This post is general information, not legal or financial advice. Before you rely on any contract term or developer agreement, confirm how it applies to your purchase with a real estate attorney or the right professional.

Quick Answers

Does this affect existing Auburndale homes? The developer agreements in city records cover new development waiting for wastewater capacity. They don't cover homes already connected to the system.

When will the Southern Force Main be finished? Phase II was approved on October 5, 2026, with 180 days to substantial completion and 210 to final completion under the contract. The city decides when the line counts as operational.

Is the treatment plant expansion scheduled? The proposed budgets spread construction money across FY 2027 and FY 2028. As of the March 2026 workshop, design hadn't moved past feasibility work.

If you're considering a new build in Auburndale's Lakes District or deciding when to list a home near it, Premier Realty Network can help you check which sewer line a community depends on before you sign. Schedule a complimentary home consultation with our Lakeland experts.